Fabrication
IN-PROCESS INSPECTION
The following activities shall be performed during in-process inspection:
- QC inspector shall check the cleaning of fit-ups prior to start of welding.
- QC inspector shall check the preheating requirement as per WPS.
- QC inspector shall check the correct WPS, welder and welding consumables required for the joint to be welded.
- QC inspector shall check the purging requirement for SS welding.
- Each welder shall check the inter-pass temperature with the tempil stick, and the QC inspector shall monitor the inter-pass temperature.
- QC inspector shall monitor the requirement of protection due to weather conditions.
- QC inspector shall record the welder number adjacent to each joint.
- QC inspector shall monitor the baking, holding, issue and return of welding electrodes.
- QC inspector shall monitor the use of specific SS tools and wire brushes for the welding of SS materials.
- QC inspector shall verify the identification tag of each piping spool.
Reference Procedures
- PCR-QCP-11 : Carbon Steel & Stainless Steel Piping Fabrication and Installation Procedure
- PCR-QCP-12 : Welding Consumable Control Procedure
- PCR-QCP-13 : Welding Control Procedure
Fabrication 23
NDE
- NDE shall be carried out in accordance with the approved procedure of WPS and NDE piping matrix.
- NDE shall be carried out after 24 hours of welding completion.
- The NDE technicians shall prepare the NDE reports, which shall be endorsed by the welding inspector.
- Should NDE examination reveal weld defect, weld repair shall be carried out using the approved WPSR. The repaired weld shall be re-radiographed. Repair shall be limited to a maximum of two attempts. Third repair shall be subject to cutout.
- The welding inspector shall keep a summary record of the welder’s performance. The frequencies of weld repair rate shall be monitored on a weekly basis, based on individual performance and the project overall.
Quality Assurance and Quality Control
- Inspection records shall be properly recorded and maintained with proper identification for each welded joint.
- Inspection shall be carried out as per approved procedure, and the results shall be recorded properly.
- Safety procedures shall be strictly followed in each inspection procedure, and in handling the inspection equipment and work environment.
-
Checklist for spool release:
- Conformance to construction and installation specifications.
- Identification and control of materials.
- Personnel are adequately qualified by certification, experience or training.
- Conformance to inspection (QC) and work performance procedures.
- Conformance to record-keeping requirements.
- Control of non-conforming items.