Fabrication
TRANSPORTATION
- Transportation of piping spools shall be carried out as per the erection sequence at site.
- The piping engineer/supervisor shall prepare the internal packing list and issue it to the material controller for the release of piping spools from the storage yard.
- Care shall be taken during loading and unloading so as to not damage the materials as well as the painted surface.
- Fabricated pipe spools shall be blocked, strapped or otherwise held in position during shipment and shall be further separated by dunnage as may be necessary to prevent damage.
- After receiving the piping spools at site, the site supervisor shall verify the identification tags and endorse the internal packing list that shall be returned to the material controller.
- Piping spools shall not be shifted to site without the knowledge of the material controller. After receiving the internal packing list from the site supervisor, the material controller shall update his spool storage summary sheet.