MATERIAL ISSUE/CONTROL
Procedure
- All pipes, fittings, valves, gaskets, stud bolts, nuts, etc., shall be controlled by the MCr.
- MCr shall maintain the summary of the total materials required for the project; the material receipt shall be issued and returned after completion.
- Materials shall be issued only based on the AFC drawing requirements.
- Additional/extra materials shall not be issued unless approved by the construction manager/PM.
- Any materials required for item modification/changes shall be approved by the client, and the details shall be available with the MCr.
- Materials shall be issued only to the personnel authorized by the PM.
- Materials shall be issued after the approval of “Store Issue Note.”
- MCr shall update the stock card after every issue.
Material Issue/Control Activity – DOs and DON’Ts
| DOs | DON’Ts |
|---|---|
| MCr shall be appointed prior to receiving any materials. | Don’t issue materials to unauthorized personnel. |
| Prepare a secured storage area prior to receiving the material. | Don’t issue additional materials without authorization. |
| Prepare separate storage containers for storing the critical materials before receiving the same. | Don’t interchange the materials received for one drawing/system to another drawing/system. |
| Issue materials only with “Store Issue Note.” | Don’t forget to update the inventory on a daily basis to prevent a stock‑out situation. |
| Update stock card on a daily basis. |