SOURCE INSPECTION AT VENDOR PREMISES
Source inspection shall be coordinated and scheduled by the Source Inspection Coordinator (SIC), and the inspection shall be performed in two categories:
- Local purchase orders – the SIC will expedite this inspection through the QA/QC department.
- Overseas purchase orders – the SIC will expedite this inspection, either with the QA/QC department personnel or by using a third-party inspection agency.
Key Documents to be Issued by SIC
Prior to proceeding with the source inspection, the SIC, as a minimum, shall issue the following documents to the inspector:
- Purchase order/work order
- Applicable client specification
- Client-approved ITPs, procedures, method statements, etc.
- Client-approved welding procedures, NDT and testing procedures
- Client-approved FAT procedures
- AFC drawings
- Client-approved product data sheets
Source Inspection Activity – DOs and DON’Ts
| DOs | DON’Ts |
|---|---|
| Pre-inspection meeting (for long lead delivery items). | Don’t start the work without approved PO/WO. |
| Availability of client-approved documents. | Don’t start the work without client-approved documentation. |
| Availability of competent resources with vendor. | Don’t deploy incompetent inspectors (PCR and TPI) to perform inspection. |
| Availability of materials/status (all MTCs shall be either “ORIGINAL” or “CERTIFIED TRUE COPY” signed and stamped by TPI). | Don’t deploy inspectors (PCR and TPI) without client approval. |
| Establish the method of resolving technical queries and application of deviation request. | Don’t allow the vendor to substitute the materials without client approval. |
| Establish the method of communication. | Don’t allow the vendor to proceed from one stage to another without client approval (for WITNESS & HOLD POINTS). |
| Establish the method of reporting progress, schedule, recovery plan, and non-conformances. | Don’t allow the vendor to deliver the materials without completion of FAT and closing of punch list. |
| Establish the inspection and test schedule. | Don’t allow the vendor to deliver the materials without client approval of final documentation, including inspection and release of warranty/guarantee certificates. |
| Establish the date of FAT. | |
| Establish the date of final inspection. | |
| Establish the contractual delivery date. | |
| Establish the final documentation requirements. | |
| Establish the logistics methods. |