INSULATION
- Check that insulation installation is in accordance with specification and AFC drawings.
- Check that insulation sealing is completed to prevent the ingress of water or moisture.
- Check that access point is provided in accordance with specification for corrosion monitoring.
- Ensure that insulation is installed after NDT hydro test and painting is completed. Perform paint touch-up, if required.
- Check that the direction of flow/color coding is indicated on the insulation cladding.
- Ensure that oil, grease, rust and other foreign matter are removed from the piping outer surface prior to installation of insulation.
- Check that longitudinal joints between segments are staggered.
- Ensure that the insulation system is provided with 15 mm diameter drain hole for every three meters length and/or follows the approved project insulation specifications.
- Check that personal protection items, such as open guard, shield, wire mesh or railings do not obstruct operational access.
- Ensure that removable insulation for flanges and valves shall be suitable for quick removal and reinstallation.
- Produce a defect list for issuance of punch list.