PAINT TOUCH-UP
- Verify that all piping activities have been completed.
- Ensure that all piping ITRs have been completed and are available.
- Ensure sharp edges are removed prior to application.
- Ensure all masking is completed.
- Ensure piping supports are painted.
- Ensure spot painting is performed.
- Ensure dry film thickness is checked and corrected.
- Record any defective area(s) on punch list.
- Check attached drawing(s) with highlighted piping sections.
- Ensure line numbering is according to P&ID.
- Ensure flow direction is according to P&ID.
- Ensure color coding is according to project requirements.
- Ensure tagging of manually operated valves is correct.
- Check that all safety/warning signs are in correct locations.