Pressure Testing
a) Hydro Test
- Verify that all piping construction/installation activities as per test package limit have been completed.
- Ensure that water flushing has been completed.
- Ensure that pre-test preparation is complete and pre-hydro test is attached together with P&ID where test limits are clearly marked.
- Ensure preliminary piping punch list is attached and all “A” items on line are cleared and signed off.
- Ensure calibration certificates for recorders and gauges are attached.
- Ensure instruments as stated in CSP 22 are removed.
- Ensure test temporaries are installed.
- Ensure permit to work or HSE authorization is in place.
- Verify release for pressure test.
-
Record data as below as per CSP 22:
| Pressure |
Temperature |
Remark |
| 0% | | |
| 25% | | |
| 50% | | |
| 75% | | |
| 100% | | |
- Pressure test to complete.