Prior to Release for Pressure Test
The following shall be fulfilled and signed off by the commissioning engineer and manager.
a) Pipe Work Completion
- Check the piping is constructed according to the latest IFC revision of P&ID and isometric drawing.
- Check that materials used are as per specification.
- Check that piping routing does not obstruct the access for emergency escape and maintenance.
- Check piping line sloping, if required.
- Ensure maintenance accessibility for valves, PSV, sample point, corrosion probe, etc.
- Check that flange rating or gray lock hubs are correct.
- Check that gaskets are provided as per specification and QA/QC report.
- Check that flange joint is properly aligned and within acceptable tolerance and tallies with QA/QC report.
- Check bolts and nuts are adequately tightened and of correct length.
- Check that required vent and drain points are provided.
- Inspect all valves and ensure that the type, size, material and flow directions are correct.
- Check filter/strainer body and inspect internal elements for damages.
- Check that filter/strainer element materials and mesh size are correct.
- Check that pipe supports are constructed and installed according to drawings.
- Check that welded joints have been completely inspected.
- Check that actuated valves are correctly installed.
- Check that piping penetrations are constructed according to drawings with sufficient stiffening plates and adequate sealing.
- Check that all piping special items are installed properly.
- Check that spectacle blinds, spades and spacers are provided and installed at location and positioned as per P&ID.
- Ensure exposed portions of spectacle blinds are coated with grease to avoid corrosion.
- Ensure that all instrument drains lead to the drain system.
- Verify that check valves and globe valves are installed in their correct flow direction.
- Check that lines are labelled at visible locations.
- Check that mating of dissimilar material is installed correctly.
- Check that all chain wheels and extended spindles required for specified valves have been installed.
- Check the isolation gasket is installed, if required.
- Ensure PSV system is installed and calibrated.
- Check the spring hanger condition is in locked position, if required.
b) Pre-Hydro Test
- Verify to ensure that all piping construction/installation activities as per test package limit have been completed.
- Ensure that the test package can be applied.
- Check that all weld inspection and NDE are complete with traceability and history records complete and cleared by QA/QC department.
- Ensure that conformity line check has been performed.
- Ensure that test package, including the attachment, is completed.
- Check that all vents and drains are installed (add temporary vents and drains for testing as required).
- Ensure all check valves are removed or tied back.
- Ensure ball valves are half-opened during test and fully opened for flushing.
- Verify that globe valves are fully opened for testing and flushing.
- Check that all temporary equipment stops, spades, bobbin pieces and supports for pressure test are installed and recorded for checking at post-test reinstatement.
- Check that all instrument relief valves, bursting discs and specified control valves have been removed for pressure test.
- Ensure all orifice flanges are blinded off.
- Ensure essential supports are fitted and springs and bellows are gagged during test.
- Check that all sprinkler heads, rosettes and nozzles have been removed and connections plugged.
- Raise piping punch list and ensure all Category A items are cleared.
c) Flushing
- Verify that all piping construction/installation activities as per test package limit have been completed.
- Check that injection points and drain-out points are completed as per test pack markup.
- Ensure that water quality is good, with maximum 30 ppm chlorite and demineralized water for stainless steel line.
- Verify equipment is bypassed and blinded.
- Check valve status in accordance with flushing and testing procedures.
- Ensure all low point drains and high point vents are flushed.
- Ensure that all piping lines in this test package have been flushed.
- Ensure that piping system has been drained out, followed by drying.
- Protect/preserve the piping system. If it cannot be done immediately, ensure that hydro testing of the same piping is completed.
- Record data as below: