Pre‑commissioning

TEST PACK / ITRs (Inspection and Test Reports)

ITRs shall be completed during construction and checked against every discipline, which will confirm correct and complete installation. The construction mechanical completion team is responsible for performing the ITR-A/B. The minimum signatories for ITR-A/B are the discipline engineer or project engineer, and review is by the commissioning manager / HUC coordinator.

ITR No. Construction Pre-Commissioning Commissioning
P01 P01-A Pipe Work Completion P01-B N/A P01-C N/A
P02 P02-A Pre-Test P02-B N/A P02-C N/A
P03 P03-A Flushing P03-B N/A P03-C N/A
P04 P04-A Pressure Test P04-B Reinstatement Work P04-C System Commissioning Leak Test
P05 P05-A Blowing/Drying P05-B N/A P05-C N/A
P06 P06-A Flanges Alignment P06-B Flanges Management P06-C N/A
P07 P07-A Bolt Tensioning / Torquing P07-B N/A P07-C N/A
P08 P08-A Chemical Cleaning P08-B N/A P08-C N/A
P09 P09-A Re-Installation Work P09-B N/A P09-C N/A
P10 P10-A Service Test P10-B Service Test P10-C N/A
P11 P11-A Pipe Painting / Coating / Marking P11-B N/A P11-C N/A
P12 P12-A Pipe Insulation P12-B N/A P12-C N/A
P13 P13-A Critical Valve Leak Test P13-B N/A P13-C N/A
P14 P14-A N/A P14-B Witness Joint P14-C N/A
P15 P15-A N/A P15-B Lube Oil Flushing P15-C N/A
P16 P16-A N/A P16-B N/A P16-C Nitrogen Purging